Selkirk Regional Health Centre Expansion

Selkirk Health Centre Expansion Website

Selkirk Regional Health Centre Expansion

Exterior of the new 30 bed inpatient addition at Selkirk Regional Health Centre.

As announced in December 2021, the Government of Manitoba is enhancing health services at Selkirk Regional Health Centre. The investment will fund a significant expansion of the facility, increasing acute care inpatient beds by 30, expand treatment capacity within the emergency department, and enhancing Selkirk’s ability to treat and monitor patients. The emergency department renovation is completed as of March, 2024.

The site, which provides a wide variety of health services for the region, will be further established with more services, including surgical and inpatient care. The new beds will allow care to be delivered locally for an increased number of inpatients and a higher volume of surgical and endoscopy patients. Surgeries performed at the site will be increased when the renovations are complete. Endoscopy procedures performed at the site have already been increased.

We’re hiring!

We're hring in Selkirk! Visit: ierhacareers.ca

News

Architectural Photos

Architectural rendering of new expansion. Glass windows and limestone exterior.
Architectural rendering of new 30 bed addition.

Project details

Inpatient addition:

The main floor addition is 28,627 sq.ft. and will provide 30 new inpatient beds and supporting services. It is divided into three areas – Medicine 3, Medicine 4 and a core area

Medicine 3:

  • 17 private rooms with washrooms
  • One bariatric isolation room
  • Med prep room
  • Therapy tub room
  • Central care station
  • Multiple satellite workstations
  • Multi-use work room

Core:

  • Physician lounge with lockers
  • Lift and equipment storage
  • Electrical and mechanical room
  • Lab storage and tech office
  • Clinical team manager and clinical resource nurse offices
  • Patient lounge and staff room

Medicine 4:

  • 11 private rooms with washrooms
  • One bariatric isolation room
  • Central care station
  • Report room
  • Satellite workstation

Emergency department redevelopment:

Interior renovations to the emergency department (718 sq. ft.) have concluded

  • Addition of two new treatment rooms and one new treatment station
  • New door with full glass panel to the Registration/Triage desk
  • New access control door hardware at door connecting to existing facility

Targeted Completion

Late 2024

Construction Update

Project is 95 % complete

Inpatient Unit Addition

Core:

  • Addition is drywalled, painted, ACT grid installed and flooring almost complete
  • Mechanical and electrical ceiling finishes in rooms are complete

Medicine Units 3 & 4:

  • Wood slat ceiling in corridor has been installed
  • Flooring is complete
  • Final coat of paint is complete (pending final deficiencies)
  • Patient lift tracks are complete
  • Systems furniture is complete (pending deficiencies)
  • Sound absorptive panels in the clerestory are 95% complete
  • Roller shade and curtain track are installed
  • Wall rail is installed

May 2024 – Excitement in building!

Timeline

March to July 2024
	Recruitment & on-boarding for both medicine units 
August 1, 2024
	Construction ends & facility handed over to IERHA
August 2024
	Staff orientation and training for 18 bed medicine unit
September 1, 2024
	First patient day for 18 bed medicine unit

	Staff orientation and training for 12 bed medicine unit
November 1, 2024
	First patient day for 12 bed medicine unit
in patient room with millwork completed and the head wall attachments for the bed.
Patient Room